Project Updates

Jay Street Improvements: Spring 2025

Metroplex, in cooperation with the Jay Street Business Association (JSBA), will be making improvements on Jay Street over the next couple of months.

Improvements on Jay Street Continue:

  • March 24 – March 28 – Work will begin to install a new tree and tree surround in front of 142 Jay Street. The existing tree in front of 156 Jay Street will get a new tree surround.
  • March 28 – April 4 – The existing alleyway arches will be removed.
  • April 7 – April 11 – New alleyway arches will be installed.

The alleyways will be intermittently closed until starting March 24 until construction is completed. Alternative routes from the Center City Lot here and from the Clinton North Lot here.

Work will begin in the mornings and we will do our best to limit disruption to businesses. Thank you in advance for your understanding.

ALCO Trail Extension and ALCO Tunnel: Spring 2025

Metroplex in coordination with the City of Schenectady will be making improvements to the ALCO Heritage Trail and ALCO Tunnel over the next couple of months.

Monday, March 17 – Tree and excavation work will begin at the ALCO Heritage Trail near Riverside Park, Union Boathouse and East Front Street. Please use caution.